mer, 04/08/2026 - 16:02 par Anonymous Added corresponding PDF as to this new update for Aug 14 2020 issue for berm repair failure
Ceci est la révision publiée.
lun, 08/24/2020 - 13:10 par HamiltonCSR Additional information about the Berm repair was added to the additional information. Upon repair Berm was flushed to test and it was found to still be leaking resulted in 500,000 material filled water to pass through a sewage lagoon.
ven, 08/14/2020 - 10:49 par HamiltonCSR
ven, 08/14/2020 - 09:48 par HamiltonCSR Nunavut Excavating, who constructed the berm cell and had attempted to repair the leaky berm, took water from a nearby water source and pumped it into the sewage lagoon cell to see if the repair attempt had been successful. However, the berm is still leaking so it is expected that the estimated 500,000 litres of water that was pumped into the sewage lagoon cell.
*Perhaps the term "sewage" isn't the correct terminology - the material filled is water that has passed through a sewage lagoon.
ven, 08/14/2020 - 09:48 par HamiltonCSR Nunavut Excavating, who constructed the berm cell and had attempted to repair the leaky berm, took water from a nearby water source and pumped it into the sewage lagoon cell to see if the repair attempt had been successful. However, the berm is still leaking so it is expected that the estimated 500,000 litres of water that was pumped into the sewage lagoon cell.
*Perhaps the term "sewage" isn't the correct terminology - the material filled is water that has passed through a sewage lagoon.
mar, 06/30/2020 - 11:27 par station Attached are two maps showing where the spill originates and the directions of the flow Also, I was just advised that the contractors that are to repair the berm are in the community and will be wanting to decant the remainder of the contents of the damaged cell. I would assume that they are required to fill out a form to send to you regarding the decanting as opposed to the spill.
Louis M. Primeau, B.Comm., CPA-CMA, CPA-CGA
Chief Administrative Officer / Director of Finance
Hamlet of Sanirajak
P.O. Box 198
Sanirajak, NU X0A OK0
P: (867) 928-8829
F: (867) 928-8871
C: (867) 222-9933
E1: sao_hbhamlet@qiniq.com
E2: dfn_hbhamlet@qiniq.com
mar, 06/30/2020 - 09:12 par station Subsequent to the filing of the spill report yesterday, the Foreman advised that the sewage lagoon cell that is leaking was not used this year until April 12th. Water deliveries from then to June 26th are estimated to be 7,843,869 litres as noted on the revised report
Louis M. Primeau, B.Comm., CPA-CMA, CPA-CGA
Chief Administrative Officer / Director of Finance
Hamlet of Sanirajak
P.O. Box 198
Sanirajak, NU X0A OK0
P: (867) 928-8829
F: (867) 928-8871
C: (867) 222-9933
E1: sao_hbhamlet@qiniq.com
E2: dfn_hbhamlet@qiniq.com
INAC: 06.20.2020 09:11 notified Justin Hack
mar, 06/30/2020 - 08:25 par snoble Lead agency changed from GN to INAC as INAC legislation covers water licences. INAC notified of change.
lun, 06/29/2020 - 09:12 par station GN: 06.29.2020 09:10 notified Sean Noble